Project 01 · Coshocton County, Ohio
Ohio Sunshine

A 2 GW solar module manufacturing plant on Papermill Road in Coshocton County, built on Ohio’s industrial workforce and located within a day’s drive of much of the U.S. population and its solar demand.
The plant
Designed for scale from day one
Ohio Sunshine is designed around two mirrored, fully automated module assembly lines running around the clock. Together they produce about 2 GW of utility-scale modules a year.
The plant will sell modules under long-term supply agreements, with toll manufacturing available to customers who supply their own cells, so line capacity is contracted before production begins. A dedicated quality organization keeps the production records that customers, lenders and tax-credit buyers rely on.
Blackstar has worked on the project since 2023, including a 2023 U.S. Department of Energy submission, and signed a purchase agreement for the Papermill Road site in February 2026.
- Site
- Papermill Road, Coshocton County, Ohio
- Site status
- Under purchase agreement (signed Feb 2026)
- Nameplate
- ~2.0 GW per year
- Building program
- ~220,000 sq ft production building
- Lines
- 2 fully automated module lines
- Product
- Utility-scale, high-efficiency modules
- Commercial model
- Module supply; toll manufacturing available
- Utility
- Service planning with AEP Ohio underway
- Workforce
- ~274 permanent roles at full operation
Status
Where the project stands
Future dates are targets and depend on financing, permitting and equipment delivery.
2023
Project launched
Plant design and U.S. Department of Energy submission.
Feb 2026
Site purchase agreement
Agreement signed for the Papermill Road site; amended July 2026.
Now
Site closing and project financing
Closing on the site and arranging construction financing.
Target: 2027
Financial close and construction start
Building works, production line delivery and installation, about 24 months to first production.
Target: late 2029
First production
Line commissioning and ramp to nameplate output.
Work with Ohio Sunshine
Capacity, supply and careers
Developers and manufacturers can join the Ohio Sunshine order book now. Ohio residents can register interest in future roles.
Quick answer
Where is the Ohio Sunshine plant, and when will it start production?
Ohio Sunshine is planned on Papermill Road in Coshocton County, Ohio. Blackstar International signed a purchase agreement for the site in February 2026. Financial close and construction start are targeted for 2027, and first production is targeted for late 2029.
| Date | Milestone | Status |
|---|---|---|
| 2023 | Project launched; plant design and U.S. Department of Energy submission | Done |
| Feb 2026 | Purchase agreement signed for the Papermill Road site | Done |
| Jul 2026 | Purchase agreement amended | Done |
| Now | Site closing and construction financing | In progress |
| 2027 | Financial close and construction start (about 24 months to first production) | Target |
| Late 2029 | First production and ramp to about 2 GW a year | Target |
Frequently asked
How large will Ohio Sunshine be?
Ohio Sunshine is planned at about 2 GW of solar modules a year from two fully automated lines in a production building of about 220,000 square feet. About 274 permanent roles are planned at full operation.
Who will supply power to Ohio Sunshine?
Blackstar International is planning utility service for the Papermill Road site with AEP Ohio.
Can buyers reserve capacity from Ohio Sunshine now?
Yes. Developers and manufacturers can place a non-binding reservation online. It takes about four minutes and needs no payment. Blackstar’s commercial team then follows up with an indicative term sheet.